The Bureau of Ocean Energy Management (BOEM) announced the approval of the Atlantic Shores South project plan to construct and operate two wind energy facilities, furthering the Biden-Harris administration’s goal of deploying 30 gigawatts of offshore wind energy capacity by 2030. This is the final approval needed from BOEM following the Department of the Interior’s July 2024 Record of Decision (ROD). Following the ROD, the original lease was divided into two separate leases, both approximately 8.7 miles offshore New Jersey at their closest points. The approved construction and operations plan includes up to 197 total locations for wind turbine generators, offshore substations, and a meteorological tower, with subsea transmission cables potentially making landfall in Atlantic City and Sea Girt, providing clean electricity to the New Jersey grid. More information is available here.